Submitter
Submitter: Reaves, Jason | Organization: Team Reaves |
Address: PO BOX 114 | City: Bauxite |
State: AR | Zip: 72011- |
Phone Number: ( ) - | E-Mail: |
Project Information
Project ID: 134680 | Manager: Jake Chatman |
Received: 8/5/2024 12:00:00 AM | Due: 8/15/2024 |
Logged: 8/5/2024 | Closed: 9/12/2024 |
Classification: Sub. Public Water/Septic Tank | Status: Closed |
Summary: | |
FREEDOM HOMES ESTATES FOUR LOT SUBDIVISION, BAUXITE,AR. TWO SETS OF PLANS/SPECS SUBMITTED, $175.00 FEE PD |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 8/5/2024 | Due: 8/15/2024 |
Date Completed: 8/12/2024 | |
Description: | |
C1 to JTC 8/12/24 |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 8/12/2024 | Due: 8/22/2024 |
Date Completed: 8/15/2024 | |
Description: | |
C1 to JTC 8/12/24 |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 8/15/2024 | Due: 8/18/2024 |
Date Completed: 8/15/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 210 | Action: Reminder to follow-up |
Date Assigned: 8/15/2024 | Due: 9/29/2024 |
Date Completed: 8/22/2024 | |
Description: | |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 8/22/2024 | Due: 9/1/2024 |
Date Completed: 9/5/2024 | |
Description: | |
See 8/21/24 email Acceptance to JC 9/5/24 |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 9/5/2024 | Due: 9/15/2024 |
Date Completed: 9/10/2024 | |
Description: | |
See 8/21/24 email Acceptance to JC 9/5/24 |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 9/10/2024 | Due: 9/13/2024 |
Date Completed: 9/12/2024 | |
Description: | |
Project manager has approved this project. |
Assigned To: 192 | Action: Billing |
Date Assigned: 9/10/2024 | Due: 9/20/2024 |
Date Completed: 9/10/2024 | |
Description: | |