Submitter
Submitter: McFAdden, William | Organization: Hope Consulting |
Address: 117 S Market Street | City: Benton |
State: AR | Zip: 72015 |
Phone Number: 501-315-2626 | E-Mail: |
Project Information
Project ID: 119195 | Manager: Jake Chatman |
Received: 4/26/2022 12:00:00 AM | Due: 5/6/2022 |
Logged: 4/26/2022 | Closed: |
Classification: Water Improvemnts(Non-Subdiv.) | Status: Open |
Summary: | |
BIG ROCK ESTATES WATER IMPROVEMENTS, BRYANT, AR. TWO SETS OF PLANS SUBMITTED, $500.00 FEE PD/$650.00 FEE PD 6/110/22 FOR SEPTIC PLANS |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 4/26/2022 | Due: 5/6/2022 |
Date Completed: 5/6/2022 | |
Description: | |
To SMY 5/6/22 |
Assigned To: 93 | Action: Supervisor Review |
Date Assigned: 5/6/2022 | Due: 5/16/2022 |
Date Completed: 5/18/2022 | |
Description: | |
To SMY 5/6/22 05/18/2022 ES REVIEWED. SMY |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 5/18/2022 | Due: 5/21/2022 |
Date Completed: 6/9/2022 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 210 | Action: Reminder to follow-up |
Date Assigned: 6/9/2022 | Due: 7/24/2022 |
Date Completed: 11/8/2022 | |
Description: | |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 10/25/2022 | Due: 11/4/2022 |
Date Completed: 11/8/2022 | |
Description: | |
A1 to RMR 11/8/22 Resubmittal by email. |
Assigned To: 179 | Action: Supervisor Review |
Date Assigned: 11/8/2022 | Due: 11/18/2022 |
Date Completed: 12/1/2022 | |
Description: | |
A1 to RMR 11/8/22 Resubmittal by email. |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 12/1/2022 | Due: 12/4/2022 |
Date Completed: 12/2/2022 | |
Description: | |
Project manager has approved this project. |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 5/24/2023 | Due: 6/3/2023 |
Date Completed: 6/8/2023 | |
Description: | |
Need updated waterline plans. Sent email to engineer on June 8, 2023. Revision to number of lots, need to revise approval letter. Sent by James Kisner by email on 5/22. |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 6/8/2023 | Due: 6/18/2023 |
Date Completed: 6/8/2023 | |
Description: | |
Need updated waterline plans. Sent email to engineer on June 8, 2023. Revision to number of lots, need to revise approval letter. Sent by James Kisner by email on 5/22. |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 6/8/2023 | Due: 6/11/2023 |
Date Completed: 6/14/2023 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 210 | Action: Reminder to follow-up |
Date Assigned: 6/14/2023 | Due: 7/29/2023 |
Date Completed: | |
Description: | |